The Plan:
Grant Hartford holds the rights to explore and extract minerals on approximately 4,000 acres surrounding the Historic Garnet Mining District. Utilizing both current and historical geological, geophysical and geochemical data, the Company designed a mining plan that it is currently implementing over the summer of 2011.
Gold Bearing Quartz Veins Report: Dr Robert Sears | January
2010
Grant Hartford Corporation 2009 Drill Report
Grant Hartford Corporation 2010 Drill Plan
43-101
Report January 25, 2011
Nancy Hanks Mine:
At the Nancy Hanks Mine we continue to
sink the decline. Infrastructure construction of the mine
office and miners showers, grounding pad and fuel depot,
mine safety and security office, pad to conduct crushing and
store ore, and a dewatering system for the mine is over 60%
complete. We are working diligently to complete this
infrastructure before the snow flies so that we may continue
underground mining operations through the winter.
Lead King Mine:
August was a good month for shipments off the Lead King
Project and we anticipate shipping a larger amount of ore
during the month of September. The weather remains dry and
optimal and we are beginning a second shift on September
12th with the intention of running 24 hours per day.
|